15 - POSTPONING THE STARTING DATE OF THE PROJECT

Due to the delay in ending the process of conditions clearing, is it possible to postpone the starting date of the project?

answer

No, as the implementation of project activities and incurred costs in the period between the date indicated as project start in the AF and the fulfillment of the conditions and signing of the Subsidy Contract is undertaken at the project’s own risk. You can ask for a project prolongation as a Major Change (namely to be approved by the MC). The extension of the project duration cannot exceed 6 months; The maximum duration of a project, including extensions, cannot be longer than 36 months for “Standard” projects.